Progress Reports

Blairgowrie Yacht Squadron provides regular progress reports on its major projects on this page. Information on the Clubhouse redevelopment project is provided by Maben whilst information on the Harbour extension project is provided by Fitzgerald Constructions.  If you have queries please contact the office on 03 5988 8453 or info@bys.asn.au

12 August 2015 update

17 July 2015 update

3 July 2015 update

19 June 2015 update

10 June 2015 update

14 May 2015 update

25 February 2015 update

3 February 2015 update

16 December 2014 update

1 December 2014 update

17 November 2014 update


Click on the thumbnail image below to view the full photo

Clubhouse construction 080915     Clubhouse construction 030915 v2     Clubhouse construction 030915

9 September 2015                   3 September 2015

Clubhouse rainbow 180815    Clubhouse driveway 180815    Clubhouse Racing Lounge 180815    Harbour construction 180815

(photos above – 18 August 2015)  

Club house construction 280715    Harbour 210715    Club house construction 180715      Club house construction 150715     Harbour construction 150715

(photos above – late July / early August 2015)                                                                                      (photos above – 15 July 2015)  

Club house construction 030715    Harbour construction 080715    Club house construction 010715     Harbour construction 010715

(photos above – 8 July 2015)                                                          (photos above – 1 July 2015     

Club house construction 240615   Harbour 170615    Harbour 100615    Clubhouse 100615    Clubhouse 100615 v2

24 June 2015                          17 June 2015                               (photos above – 10 June 2015)

Construction 270515 v2    Construction 270515    Marina construction 270515   Marina construction 270515 v2

 (photos above – 27 May 2015)

Construction 290415 v2   Construction 290415   Harbour 220415  Harbour 220415 v2   Clubhouse 220415

 (photos above – 29 April 2015)                                         (photos above – 22 April 2015)

Clubhouse 150415   Clubhouse 150415 v2   Construction 010415    Pylons v2   Pylons v3

(photos above – 13 April 2015)                                                 (photos above – 31 March 2015)   

 

Clubhouse Roofing 250315       Clubhouse inside 250315    Construction 020315 - crane v3   Construction 180315 - clubhouse

 (photos above – 25 March 2015)                                                 (11 March 2015)               (18 March 2015)


___________________________________________________________________________________________________________________

Updated: 12 August 2015

Week Ending 21/08/2015

  • Complete installation of all light fittings
  • Commence Commissioning
  • Commence detailed clean
  • Commence Carpet Tiles

Week Ending 28/07/2015

  • Complete Commissioning
  • Complete Detailed Clean
  • Complete all floor finishes
  • Complete Recycled Timber on Stair 3


___________________________________________________________________________________________________________________

Updated: 17 July 2015

Week Ending Friday 24/07/2015

  • Painting Ongoing
  • Complete Installation of First Floor Decking
  • Installation of Floor Finishes Ongoing
  • Fit Off all Sanitary Items Ongoing
  • Fit Off Electrical Items Ongoing
  • Installation of Entry Cladding
  • Install Stringers for Stair 4

Week Ending Friday 31/07/2015

  • Complete Painting
  • Installation of Stair Treads
  • Installation of Balustrades and Handrails
  • Installation of Signage
  • Installation of Bar Fronts and Feature Balustrade Timber
  • Complete Floor Finishes Installation
  • Commence Commissioning
  • Commence Defects

Fortnight Commencing 03/08/2015

  • Civil
  • Complete Defects

Procurement

  • Recycled Timber Currently in Kiln
  • Light Fittings

___________________________________________________________________________________________________________________

Updated: 3 July 2015

Week Ending Friday 10/07/2015

  • Complete Installation of Barestone Cladding
  • Complete Sheeting of First Floor Internal Walls
  • Installation of Windows On Going
  • Complete Tiling to Ground Floor
  • Complete Kitchen Installation
  • Complete Installation of Canteen
  • Complete Roller Door Installation
  • Painting Ongoing
  • Complete Installation of Ground Floor Decking
  • Installation of Northern Window Reveals
  • Commence installation of Floor Finishes
  • Fit Off all Sanitary Items
  • Commence Fit Off Electrical Items
  • Installation of Entry Cladding

Week Ending Friday 17/07/2015

  • Install Stringers for Stair 4
  • Painting Ongoing
  • Installation of First Floor Decking Ongoing
  • Installation of Stair Treads
  • Installation of Bar Fronts and Feature Balustrade Timber
  • Floor Finishes Installation Ongoing
  • Install Toilet Partitions and Benches
  • Fit Off of Electrical Items Ongoing
  • Complete Joinery

Procurement

  • Window Glazing
  • Light Fittings


___________________________________________________________________________________________________________________

Updated: 19 June 2015

Week Ending Friday 26/06/2015

  • Complete Ground Floor Internal Walls
  • Complete Installation of Barestone Cladding
  • Complete Sheeting of First Floor Internal Walls
  • Installation of Windows On Going
  • Complete Tiling to First Floor
  • Commence Tiling to Ground Floor
  • Kitchen Installation Ongoing
  • Complete Roller Door Installation
  • Painting Ongoing
  • Commence Installation of Canteen
  • Installation of Ground Floor Decking Ongoing
  • Installation of Northern Window Reveals

Week Ending Friday 03/07/2015

  • Complete Sheeting Level 2
  • Complete Installation of Windows
  • Install Stringers for Stair 4
  • Complete Kitchen Installation
  • Complete Canteen Joinery
  • Complete all Tiling
  • Painting Ongoing
  • Complete Ground Floor Decking
  • Waterproof First Floor Decking
  • Commence Installation of First Floor Decking
  • Commencement of Western Recycled Timber Façade

Procurement

  • Aluminium Windows
  • Canteen and BBQ
  • Tiles
  • Timber Currently Being Kiln Dried
  • Light Fittings
  • Feature Ceiling to Senior Lounge
  • Joinery

__________________________________________________________________________________________________________________

Updated: 10 June 2015

Week Ending Friday 12/06/2015

  • Complete Ground Floor Internal Walls
  • Installation of Barestone Cladding On Going
  • Sheeting of First Floor Internal Walls On Going
  • Installation of Windows On Going
  • Complete Installation of Lunawood
  • Tiling to First Floor On Going
  • Kitchen Installation Ongoing
  • Remaining Roller Doors to be Installed
  • Complete all Concrete Works
  • Painting On Going

Week Ending Friday 19/06/2015

  • Sheeting of Internal Walls On Going
  • Installation of Windows On Going
  • Installation of External Cladding On Going
  • Install Stringers for Stair 4
  • Kitchen Installation On Going
  • Commence Canteen Joinery
  • Tilling On Going
  • Painting On Going

Procurement

  • Aluminium Windows
  • Canteen and BBQ
  • Tiles
  • Timber Currently Being Kiln Dried
  • Light Fittings
  • Feature Ceiling to Senior Lounge
  • Joinery


___________________________________________________________________________________________________________________

Updated: 14 May 2015

Week Ending Friday 15/05/2015

  • Sheeting of Ground Floor Internal Walls On Going
  • Installation of Barestone Cladding On Going
  • Sheeting of First Floor Internal Walls On Going
  • Installation of Windows On Going
  • Install Vitrabond Panels to Ground and First Floor
  • Installation of Lunawood
  • Installation of Ground Floor Auto Doors

Week Ending Friday 22/05/2015

  • Sheeting of Internal Walls Ongoing
  • Installation of Windows On Going
  • Installation of External Cladding On Going
  • Install Stringers for Stairs 1 and 4
  • Installation of Plant Platform
  • Commence Tiling to Ground Floor Amenities and Kitchen
  • Commence Kitchen Installation

Procurement

  • Aluminium Windows
  • Kitchen
  • Tiles
  • Cladding Materials
  • Doors
  • Vinyl
  • Carpet
  • Delivery of Timber to Hastings for Milling

___________________________________________________________________________________________________________________

Updated: 25 February 2015

Week Ending Friday 06/03/2015

  • Structural Steel Erection
  • Installation of external ground floor doors
  • Complete ground floor framing

Week Ending Friday 13/03/2015

  • Structural Steel Erection
  • Installation of beer python
  • Installation of post mix python
  • Commence roof installation

Procurement

  • Aluminium Windows
  • Barestone Cladding
  • Roofing materials


___________________________________________________________________________________________________________________

Updated: 3 February 2015

Harbour Extension Update – February and March 2015

Mid-February

  • Crane arrives at BYS to facilitate site set up and pile unloading
  • Earth works to flatten site for pile storage commences
  • Site equipment and materials brought to site

March

  • Jetty piles arrive in Melbourne and transported to BYS in the first week of March
  • Mobilisation of Banut land based piling rig for immediate commencement of jetty piles.
  • Wave screen piles arrive in Melbourne and transported to BYS in the last week of March
  • Barge piling rig on site end March for immediate start
  • Hard stand piles delivered to Fitzgerald Constructions for storage

Off-site Fitzgerald Constructions will commence temporary steel works, shop drawings and steel reinforcement.

___________________________________________________________________________________________________________________

Clubhouse Redevelopment Update – Week Ending Friday 06/02/2015

  • Install external drainage
  • Install grease trap
  • Ground floor stud walls

Week Ending Friday 13/02/2015

Services Rough In

  • Form and pour plinth for stair 1
  • Clean underside of exposed concrete
  • Commence battening our for plaster

___________________________________________________________________________________________________________________

Updated: 16 December 2014

Week Ending Friday 19/12/2014

  • Form up for suspended concrete
  • Locate and block out all penetrations
  • Lay reinforcing steel
  • Install Post Tensioning cables

Week Ending Friday 26/12/2014

  • Pour suspended concrete
  • Tension cables
  • Prepare for Christmas shut down (clean up and limit compound to minimum requirements)

The Slipway is gone…for now

The first stage of the harbour construction has been completed on schedule with the removal of the slipway. The Ironbark piles came out of the water with ease. The sections that were in the sand looked the same as they did when they were first installed many years ago. The timber will now be transported to Melton where it will be stacked, air dried and then ultimately kiln dried and sawn into lengths that will then return to the club to become a feature on the exterior of the new clubhouse. The clubhouse sub-committee and the General Committee were adamant that this part of the history of BYS was going to be retained. The crossheads and other timber will remain at the club while we determined where it can be re-used. We expect the preparation process for the piles to take approximately 5 months.

___________________________________________________________________________________________________________________

Updated: 1 December 2014

Club Operations

Bellingham Marine is currently on site conducting repairs on the marina fingers and T-heads. It is anticipated that the T-Heads will be operational again for our Christmas period with visitor bookings now being taken.

Planning is underway for our busy summer season including the Boxing Day Dash. Please be aware that due to the large volume of people expected to use our temporary facilities on Boxing Day a decision has been reached to close the car park for safety.

Clubhouse Redevelopment

Maben’s latest progress report;

Week Ending Friday 05/12/2014

  • Complete ground slab
  • Complete under slab services
  • Part B of Termite Treatment
  • Erect first half of precast panels
  • Forming up of columns

Week Ending Friday 12/12/2014

  • Pour all columns
  • Commence preparing for external concrete works
  • Commence setup for first floor suspended slab

Safe Boat Harbour Expansion

MAW Civil is currently working to relocate sand from the front of the Clubhouse to the area in front of the caravan park.

The Department of Primary Industries has recently issued consent for our Coastal Management Application which is required for construction to start on the Safe Boat Harbour extension. This consent follows completion of the pre-construction planning conditions associated with the permit.

Fitzgerald Construction have delivered the majority of their site sheds to BYS in preparation for construction to commence in the coming weeks.

Communication Forums

A question and answer forum was held in the McCarthy Training Centre on Saturday 29th November 2014 for BYS members. Should members have further questions following this session please forward them to the office at info@bys.asn.au

___________________________________________________________________________________________________________________

Updated: 17 November 2014

Club Operations

BYS Club Operations continue as normal using the temporary facilities. The most recent addition to this infrastructure is the canteen site shed located next to the BYS office. The canteen will be operational from the 20th December 2014. The Club is currently working to fit this site shed out with necessary equipment, data and power requirements.

The car park boom gates have been removed to allow for construction vehicles. The car park remains accessible to only those members in possession of a car park permit.

Work is currently taking place to remove the damaged attenuator pontoon from the beach. In addition Bellingham Marine will be on site this week to commence repairs on the marina fingers and T-heads. It is anticipated that the T-Heads will be operational again for our Christmas period with visitor bookings now being taken.

Clubhouse Redevelopment

The building permit has been issued. The builders, Maben, are now on site and have started work on the Clubhouse redevelopment. They have recently installed fencing around the construction area and are in the process of moving their site sheds into position. Maben will provide regular update reports. The detail from the first of these reports is seen below.

Week Ending 14/11/2014

  • Soak pit installed
  • Sewer pit excavated and installation to be completed
  • Pad footings complete

Week Ending 21/11/2014

  • Complete all footings
  • Commence underground services
  • Commence preparation of ground floor slab
  • Termite treatment

Week Ending 28/11/2014

  • Complete underground services
  • Complete preparation of ground floor slab
  • Pour and complete all ground floor slabs

Safe Boat Harbour Expansion

BYS continues to focus on discharging the pre-construction planning conditions with all necessary reports now with MPSC and DEPI.

Fitzgerald Engineering has started to deliver site sheds to accommodate their staff in preparation for work commencing later this month.

Parks Victoria has provided the permit to start work on the sand relocation from the Blairgowrie Safe Boat Harbour. MAW Civil has been contracted to do this work which will take place between 17 Nov – 5 December 2014. This Stage 1 sand relocation work will use trucks and excavators (no dredging at this stage) to place sand above the low water mark in front of the Caravan Park.

The slipway demolition is due to start in late November. Approximately half the slipway from the front of the Club to approximately the low water mark will be removed prior to Christmas making way for the dredging that will commence in late January 2015.

 